Spring ’19 Milestones

Aircraft Design (Milestone 1): March 1, 2019 – Preliminary┬áResearch on Thermal Cooling System
Aircraft Design (Milestone 2): April 15, 2019 – Structural Models in ABACUS and Data From Analysis

Battery Team (Milestone 1): March 1, 2019 – Developed Safety Plan for the Battery
Battery Team (Milestone 2): April 26, 2019 – Completed Final Packaging Model in SolidWorks

CAD/Build (Milestone 1): February 22, 2019 – Test RC Plane and Research Possible Foam Candidates
CAD/Build (Milestone 2): April 26, 2019 – Build New Wings and Test Them on the RC Plane